Settlement FAQs

how to install settlement plates

by Ms. Delphia Hintz Published 3 years ago Updated 2 years ago
image

Settlement plates are mainly installed on existing ground surface prior to the building of an embankment.The system consists of a base plate, reference rod (riser) that can be attached via threaded couplings or using a client’s specific design.The base plate is placed on the ground with a section of riser attached then the ground and riser elevation is established prior to proceeding with placement of fill.

Full Answer

What is a settlement plate and when is it used?

Settlement plates or points are commonly installed where significant settlement is predicted (Dunnicliff, 1988) to record the magnitude and rate of settlement under a load. Therefore, they should be placed immediately after installing the vertical drains.

When to place the settlement plate of a vertical drain?

Therefore, they should be placed immediately after installing the vertical drains. In the simplest form, this instrument is a settlement plate consisting of a steel plate placed on the ground before construction of the embankment. Surface settlement points measure vertical displacement with depth, for example, along an embankment centerline.

How do you monitor settlement of a settlement?

Typically, a reference rod and protecting pipe are attached to the settlement-monitoring platform. Settlement is often evaluated periodically until the surcharge embankment is completed, then at a reduced frequency, measuring the elevation of the top of the reference rod.

How deep should a settlement rod be installed in a pipe?

The pipe shall be installed to a depth of approximately 4 ft. (1.2 m) and cleaned for its full length prior to the placement of the steel rod. 2. The pipe shall be capped except during reading operations. Figure 1Fabrication and Installation Details for Settlement Rods EB 15-025 Page 5 of 28 Figure 2 EB 15-025 Page 6 of 28 III.

What is a settlement marker?

Why is casing capped?

Why is a piezometer kept in a protective box?

How to measure depth of spider magnet?

How to measure ground water level?

image

How do I install settlement plates?

Installation & MaintenanceSettlement plates are installed at specified locations.The initial elevation of each plate and riser is noted carefully. ... Fill is hand-compacted around the riser to the specified level of the lift. ... When fill approaches the top of the riser, an extension is added and step 3 is repeated.

What is Plate settlement?

Settlement plates or points are commonly installed where significant settlement is predicted (Dunnicliff, 1988) to record the magnitude and rate of settlement under a load. Therefore, they should be placed immediately after installing the vertical drains.

How do I monitor my settlement markers?

The settlement marker is used to measure a localised settlement or heave of roads, slopes, embankments, utility pipes and cables. The monitoring of settlement marker is carried out by leveling survey and readings are taken at regular intervals to check any settlement or heave.

How do you monitor ground settlement?

Monitoring SettlementCracks in floor slabs and walls are monitored with crackmeters.Misalignment or separation of incoming utilities or expansion joints can be monitored with jointmeters.Differential settlement of floors and walls can be monitored with hydrostatic level cells.More items...

How is plate load test done?

The plate load test, which is used to determine bearing capacity and settlement, may be carried out by either using a gravity loading or truss loading method. A test pit of the same depth as the foundation and width equal to five times the size of bearing plate is dug in the ground.

How do you carry out a plate bearing test?

The test is usually carried out at foundation level. A load is applied in five increments with readings taken every minute until detectable movement of the plate has stopped. During the test the pressure exerted is added at a consistent rate.

How do Settlement markers work?

Structure settlement marker is used to monitor the movement of the existing buildings/ structures which may be affected by the works. Featuring a spherical head and a plated body that minimize damage to the building, the wall-mounted marker is installed around the external facade of the building.

What is deep settlement gauge?

Deep settlement gauges are usually installed on top of each sub-layer to monitor the magnitude of the settlement of sublayers. Measurements are usually taken using the survey method, and. Table 13.4 shows data obtained from deep settlement gauges.

How does settlement gauge work?

The system consists of a series of H-Level gauges that are connected hydraulically to a reference tank located at a stable location. Each H-Level gauge includes a high resolution pressure sensor that monitors the head of liquid resulting from the difference in elevation of the gauge and the reference tank.

How do you monitor movement in a building?

One of the most commonly used methods is crack monitoring to establish if there is ongoing movement in the building. Small metal studs are inserted either side of the cracks, and regular readings taken to ascertain whether the cracks are opening or closing. Typically, as little as 1mm movements can be detected.

What is a ground settlement?

Settlement is the downward movement of the ground (soil) when a load is applied to it. The load increases the vertical effective stress exerted onto the soil. This stress, in turn, increases the vertical strain in the soil. This increase in vertical strain causes the ground to move downward.

How is soil settlement calculated?

1. Calculation of stresses. Structures with their loads generate a stress change in the soil. In order to be able to calculate settlements in the soil due to this change in stress, it is necessary to know the spreading and distribution of the stresses in the foundation soil.

What does it mean for the ground to settle?

In geotechnical engineering , settlement is defined as the vertical movement of the ground, generally caused be changes in stresses within the earth. Subsidence is a term often used to described 'caving in' or sinking of the ground, that may not be associated within changes in soil stresses.

What is ground settlement in construction?

Introduction. Settlement is the downward movement of the ground caused by a load consolidating the soil below it or causing displacement of the soil. Settlement often refers to the downward movement of the ground around an excavated space, such as that for tunnels, shafts, or basements.

What is a settlement marker?

The settlement marker is used to measure a localised settlement or heave of roads, slopes, embankments, utility pipes and cables.

Why is casing capped?

Installed casing is capped and kept in a protective metal box to prevent damage & disturbance

Why is a piezometer kept in a protective box?

The borehole with vibratingwire piezometer installed is kept in a protective metal box to prevent damage & disturbance to the instrument.

How to measure depth of spider magnet?

Depth of the magnet is measured from the measuring tape attached to the probe.

How to measure ground water level?

Ground water level is measured by using water level indicator. The probe of water level indicator is lowered down into the water standpipe until light or buzzer indicates contact with the water.  Depth to water level is measured from the measuring tape attached to the indicator.

What is a settlement plate?

Settlement plates or points are commonly installed where significant settlement is predicted (Dunnicliff, 1988) to record the magnitude and rate of settlement under a load. Therefore, they should be placed immediately after installing the vertical drains. In the simplest form, this instrument is a settlement plate consisting of a steel plate placed on the ground before construction of the embankment. Surface settlement points measure vertical displacement with depth, for example, along an embankment centerline. Typically, a reference rod and protecting pipe are attached to the settlement-monitoring platform. Settlement is often evaluated periodically until the surcharge embankment is completed, then at a reduced frequency, measuring the elevation of the top of the reference rod. Benchmarks used for reference data must be stable and remote from all other possible vertical movements. Further information about settlement points is given elsewhere ( Dunnicliff, 1988 ).

How many settlement plates were installed over the trial embankments?

Sixteen settlement plates were also installed over the trial embankments, and the total vertical displacements of the eight vibrating wire settlement gauges were also measured. Figure 17.9 shows the vertical deformation of sublayer 2.

Why was the reinstated embankment not monitored?

The reinstated embankment was not monitored except for settlement during and after construction. Base settlement plates were installed above the bottom layer of geotextile to measure base settlement. Measurement was discontinued due to unforeseen circumstances on August 21, after an accumulated settlement of about 300 mm.

How much pressure is required for stone column ground improvement?

It is evident from the load test that the proposed scheme of stone column ground improvement is adequate to carry the working loading pressure with acceptable short-term and long-term settlement specifications as well as to sustain loading pressure of 500 kPa with acceptable settlement. Subsequent operation of the yard has proven that the stone column ground improvement method has strengthened the existing ground to meet the target performance criteria.

How to calculate secondary consolidation settlement?

The primary consolidation settlement can be calculated from the coefficient of volume compressibility mv, which can further lead to the Young’s modulus E′ = (1 + v′ ) (1 − 2 v′ )/ [ mv (1 − v′ )] , with an assumed Poisson’s ratio v′. The secondary compression settlement (creep) can be estimated from the secondary compression index Cɛα = Cα / (1 + e0 ), where Cα is the coefficient of secondary compression and e0 is the initial void ratio.

What is plate load test?

Plate load tests were conducted after the completion of ground improvement works to verify quality and effectiveness. The plate was designed to simulate loads imposed by crane track ( Fig. 11.26 ). Figure 11.27 shows that under working plate loading pressure of 370 kPa, the measured plate settlement was only about 24 mm. At plate loading pressure of 500 kPa, the measured plate settlement increased to about 60 mm. At the final plate loading pressure of 600 kPa, the measured final plate settlement was about 95 mm.

How much lateral movement is there at the abutment of a bridge?

The maximum measured settlement and lateral deformation at the bridge abutment location was 20–40 mm under the 5.5 m embankment fill. Excessive lateral movement of 100 mm was observed above the ground level due to disturbance caused by the construction of the protection bund. Based on the monitoring results, the postconstruction ground deformations (40 years after road opening) at the bridge abutment are likely to be lower than the design values predicted.

When to install settlement rods?

Settlement rods shall be installed as shown in Figure 1 at the locations shown on the plans immediately after embankment or surcharge construction is completed . The elevation of the top of the steel rod at the time of the installation shall be determined and recorded. The exposed length of pipe shall be made conspicuous, to reduce the chance of damage.

What is the settlement rod manual?

This manual establishes uniform statewide procedures for fabrication, installation, documentation, maintenance and disposal of settlement gages and settlement rods.

How does a manometer surface settlement gage work?

The manometer gage works on the principle that a fluid seeks its own level. The fluid line reflects any change in elevation between the base and readout box. The air line maintains the same atmospheric pressure at the base that exists at the readout box. The distance between the readout box and base should not exceed 230 ft. (70 m).

How to install a gage on a foundation?

These gages shall be installed at locations designated on the plans by driving or pressing the anchor post, using the outside casing (NPS 1) , from the surface of the embankment foundation to the elevation specified in the plans (see Figure 7). The anchors post shall then be expanded by tapping, with a small sledge hammer, the inside pipe (NPS ¼) while the outside casing is held in a fixed position. A 3 ft. (1 m) piece of pipe is now added to the inside pipe, wit the inside pipe held in a fixed position, the outside casing shall be detached at the left-hand threaded connection and retracted about 3 ft. (1 m) (see Figure 6).

When are settlement gages and rods abandoned?

All settlement gages and rods shall be abandoned after termination of the construction waiting period, unless the Geotechnical Engineering Bureau requests in writing that installations be retained for future readings. Procedures for abandonment are as follows:

What is a pipe surface settlement gage?

A pipe surface settlement gage indicates total foundation settlement behavior during and after embankment construction.

How deep should a steel pipe be installed?

Notes:1. The pipe shall be installed to a depth of approximately 4 ft. (1.2 m) and cleaned for its full length prior to the placement of the steel rod. 2. The pipe shall be capped except during reading operations.

What is a settlement marker?

The settlement marker is used to measure a localised settlement or heave of roads, slopes, embankments, utility pipes and cables.

Why is casing capped?

Installed casing is capped and kept in a protective metal box to prevent damage & disturbance

Why is a piezometer kept in a protective box?

The borehole with vibratingwire piezometer installed is kept in a protective metal box to prevent damage & disturbance to the instrument.

How to measure depth of spider magnet?

Depth of the magnet is measured from the measuring tape attached to the probe.

How to measure ground water level?

Ground water level is measured by using water level indicator. The probe of water level indicator is lowered down into the water standpipe until light or buzzer indicates contact with the water.  Depth to water level is measured from the measuring tape attached to the indicator.

image
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z 1 2 3 4 5 6 7 8 9